Risk assessments and method statements RAMS
Contents |
[edit] Introduction
RAMS are Risk Assessments and Method Statements.
[edit] Risk assessments
The Construction (Design and Management) Regulations (CDM Regulations) are intended to ensure that health and safety issues are properly considered during a project’s development so that the risk of harm to those who build, use and maintain structures is reduced.
They require that as the design progresses, risks are identified and eliminated and residual risks are reduced and managed and that designers, principal designers, principal contractors and contractors take account of the 'principles of prevention' in carrying out their duties, which in general terms are:
(a) Avoid risks where possible.
(b) Evaluate those risks that cannot be avoided.
(c) Put in place proportionate measures that control them at source.
Whilst the specific process of preparing a formal risk assessment is not a requirement of the CDM regulations, regulation 3(6)(a) of the Management of Health and Safety at Work Regulations does require that risks are controlled in the workplace, including construction sites. This involves thinking about what might cause harm to people and deciding what steps to take to prevent that harm. Where an employer employs five or more people, the significant findings of risk assessments must be recorded.
For more information, see Risk assessments.
[edit] Method statements
Method statements are widely used in construction as a means of controlling specific health and safety risks that have been identified (perhaps following the preparation of a risk assessment) such as; lifting operations, demolition or dismantling, working at height, installing equipment, and the use of plant.
A method statement helps manage the work and ensures that the necessary precautions have been communicated to those involved.
Like risk assessments, producing written method statements is not an explicit requirement of the CDM Regulations, however they are identified by the Health and Safety Executive as one way of satisfying the requirements of the regulations and as an effective means of assessing risks, managing risks, collecting workers’ views and briefing workers.
Method statements need be no longer than is necessary for them to be effective. They are for the benefit of those carrying out the work and so should be clear, should not be overcomplicated and should be illustrated where necessary.
For more information, see Method statements
[edit] RAMS
So, generally a risk assessment is undertaken to identify (and where possible eliminate) risks, and then a method statement is prepared to control residual risks.
They are sometimes described together as 'RAMS'. RAMS may be required by third parties to demonstrate that health and safety has been properly considered and that the requirements of the CDM regulations have been satisfied. For example, a contractor may require submission of RAMS form sub-contractors, a landlord may require submission of RAMS from tenants proposing to carry out works to a property, or a client may require submission of RAMS from contractors operating on their premises.
[edit] Related articles on Designing Buildings
- As Low As Reasonably Practicable (ALARP).
- CDM.
- Contractor.
- Deleterious materials.
- Demolition.
- Design risk management (DRM)
- Health and safety.
- How to write a method statement.
- Method statements.
- Permit to work.
- Principal contractor.
- Project execution plan.
- Risk assessment.
- Risk feedback.
- Site records and registers.
- Temporary works.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.


























Comments
Excellent, very helpful. I just bookmarked the website.